Short answer

Most small jobs, such as a room, a garage or a rim joist, take one day. Medium jobs such as a pole barn or a whole house take two to four days, and large commercial or residential projects take a week or more. After the last pass, add the re-occupancy time, typically 24 hours, before the space is back in use.

FoamGuard

How FoamGuard handles it

  • In writing: your agreement states the approximate start and completion dates (Section 7), and we give you the re-occupancy time for the product in writing (Section 11).
  • What sets the length: the board feet, the number of passes the thickness needs, access and lifts, and how much masking the space takes.
  • Weather and temperature: foam has substrate and air temperature limits. If the day falls outside them, the date moves and the price doesn't (Section 7; see spray foam in winter).
  • Booking lead time runs from about 2 to 16 weeks depending on the season and the size of the job.
  • Multi-day jobs: the arrival-time texts go out each morning, and the request to clear the spray area goes with the first day's.

From the Project Agreement, Sections 7 and 11.

Industry

What's typical elsewhere

Days on site vary with the same factors for every contractor, which is why consumer cost guides list "How long will the project take?" among the questions to ask before you hire (HomeGuide). Pennsylvania requires a home improvement contract to state the approximate start and completion dates (73 P.S. § 517.7(a)(6)).

Job sizeExamplesDays on site
SmallA room, a wall, a garage, a rim joist1 day
MediumA pole barn, a whole house, an attic roof deck2–4 days
LargeCommercial buildings, large residential7 days or more

Want a number for your own project? Price My Project, book a free visit or call (814) 208-3478.

More on this

Can foam be sprayed in winter?

Yes, within the product's temperature limits for the surface and the air. Cold-weather jobs use a winter-grade foam.

Do I need to stay out every night of a multi-day job?

Plan to stay out of the work area while spraying and for the re-occupancy time after the last pass in it. We set the plan for your building at the quote.

Why does a small job wait longer for a date?

Small jobs are grouped with other work near you, so the date depends on when we are already working in your area.